ON BUDGET - The wastewater transmission system connecting Lacombe, Blackfalds and Lacombe County to the regional wastewater treatment facility in Red Deer is on budget and progressing well. photo submitted

Lacombe to Red Deer regional wastewater facility on budget

Project expected to cost approximately $71 million

The North Red Deer Regional Wastewater Services Commission (NRDRWWSC) is pleased to report that construction on the wastewater transmission system connecting Lacombe, Blackfalds and Lacombe County to the regional wastewater treatment facility in Red Deer is on budget and progressing well.

Six construction contracts are underway concurrently. Pipeline construction from the Odour Management Facility to the City of Red Deer’s Wastewater treatment Plant is expected to be completed ahead of schedule in November 2017. PVC installation was completed by mid-October, and the entrance chamber construction is on-going and nearly complete.

Construction of the Odour Management Facility is on track for completion on schedule by mid-January 2018. Precast concrete walls are up and work on the building roof is ongoing.

Construction on the pipeline from Blackfalds to the Odour Management Facility is on schedule. Crews are currently installing pipe North of Highway 597, including well point dewatering. Pressure testing completion is set for Dec. 15th, 2017.

Construction of the Blackfalds Lift Station is on schedule for completion in late January 2018. PVC site piping is being completed and the precast concrete walls are up and roof work is ongoing.

Pipeline construction from Lacombe to Blackfalds, is ahead of schedule. Crews are working on pipe installation towards Lacombe (Range Road 264) and along Highway 597. Pressure testing completion is set for Dec. 15th, 2017.

Construction of the Lacombe Lift Station is on schedule for completion in late February 2018. All cast-in-place concrete work has been completed and all underground pipe and backfilling to grade level has been completed.

Construction completion of the overall project is scheduled for Mar. 31st, 2018. The project is expected to cost approximately $71 million. Funding partners for the project include the Government of Canada, the Alberta Government and the NRDRWWSC municipal partners (City of Lacombe, Town of Blackfalds, and Lacombe County) as well as the City of Red Deer.

For more information, please visit www.nrdrwwsc.ca.

—Connolly

Just Posted

Lacombe Composite High School Cosmetology students hosts Hair Massacure

Fundraiser supports kids battling pediatric cancers

Lacombe Council asks for answers regarding Police Service deficit

Lacombe Police Service ran a $238,627 deficit in 2018

City of Lacombe releases 2018 Audited Financial Statements

City had an operating surplus of about $318,000

Wolf Creek Public Schools board meeting – April 18th, 2019

Board approves international field trip; deliberates budget; discusses dangers of vaping

Lacombe Generals honoured by City for winning Allan Cup

2019 Allan Cup champs celebrated after successfully hosting tournament

VIDEO: Police dog in Oregon struck by 200 porcupine quills during pursuit

The German shepherd had to be sedated and was in treatment for more than two hours

Amber alert issued for 5-year-old Ontario boy

Ethan Montes is believed to be in the company of his mother, 47-year-old Juliet Mohammed

Calgary woman killed in B.C. highway crash

Crash closed highway for hours

Assessment says Alberta woman facing animal abuse charges fit to stand trial

April Dawn Irving, 59, is charged with 13 counts of cruelty to animals

Canadian privacy watchdogs find major shortcomings in Facebook probe

The probe followed reports that Facebook had let an outside organization use an app to access users’ personal info

Provinces, Ottawa talk 50/50 split on abandoned bus-route service

B.C. has paid $2 million on a bus service for the northern part of the province

Wilson-Raybould: Feds want to just ‘manage the problem’ of Indigenous Peoples

Former federal justice minister speaks at First Nations Justice Council meeting in B.C.

Oil and gas company confirms death of one of its employees in Yoho avalanche

Dana Coffield died when he was skiing in the Rocky Mountains

Cenovus CEO estimates production curtailments will deliver billions to taxpayers

The curtailment program started Jan. 1 was designed to keep 325,000 barrels per day off the market

Most Read