ON BUDGET - The wastewater transmission system connecting Lacombe, Blackfalds and Lacombe County to the regional wastewater treatment facility in Red Deer is on budget and progressing well. photo submitted

Lacombe to Red Deer regional wastewater facility on budget

Project expected to cost approximately $71 million

The North Red Deer Regional Wastewater Services Commission (NRDRWWSC) is pleased to report that construction on the wastewater transmission system connecting Lacombe, Blackfalds and Lacombe County to the regional wastewater treatment facility in Red Deer is on budget and progressing well.

Six construction contracts are underway concurrently. Pipeline construction from the Odour Management Facility to the City of Red Deer’s Wastewater treatment Plant is expected to be completed ahead of schedule in November 2017. PVC installation was completed by mid-October, and the entrance chamber construction is on-going and nearly complete.

Construction of the Odour Management Facility is on track for completion on schedule by mid-January 2018. Precast concrete walls are up and work on the building roof is ongoing.

Construction on the pipeline from Blackfalds to the Odour Management Facility is on schedule. Crews are currently installing pipe North of Highway 597, including well point dewatering. Pressure testing completion is set for Dec. 15th, 2017.

Construction of the Blackfalds Lift Station is on schedule for completion in late January 2018. PVC site piping is being completed and the precast concrete walls are up and roof work is ongoing.

Pipeline construction from Lacombe to Blackfalds, is ahead of schedule. Crews are working on pipe installation towards Lacombe (Range Road 264) and along Highway 597. Pressure testing completion is set for Dec. 15th, 2017.

Construction of the Lacombe Lift Station is on schedule for completion in late February 2018. All cast-in-place concrete work has been completed and all underground pipe and backfilling to grade level has been completed.

Construction completion of the overall project is scheduled for Mar. 31st, 2018. The project is expected to cost approximately $71 million. Funding partners for the project include the Government of Canada, the Alberta Government and the NRDRWWSC municipal partners (City of Lacombe, Town of Blackfalds, and Lacombe County) as well as the City of Red Deer.

For more information, please visit www.nrdrwwsc.ca.

—Connolly

Just Posted

WATCH: Alberta Party leadership candidates present visions to Central Albertans

Party members will vote for their new leader on Feb. 7th

Excitement is building about Lacombe hosting 2019 Allan Cup

Six teams, representing six regions nationally, will take part in the Allan Cup in April 2019

Lacombe and Red Deer Chambers prepare members for cannabis legalization

Luncheon speaker educates businesses on marijuana policies

Lacombe Generals to host 2019 Allan Cup

The Allan Cup was last hosted in Alberta in 2013 in Red Deer

Rogers Hometown Hockey lands in Lacombe Feb. 3rd and 4th

The weekend will feature broadcast hosts Ron MacLean and Tara Slone, meet-and-greets with NHL alumni and activities for the whole family

UPDATE/WATCH: Jason Klaus and Josh Frank guilty in triple murder

Crown argues for 75 years to life in prison, sentencing on Jan. 22nd

Bad timing: Shutdown spoils Trump’s one-year festivities

Trump spends day trying to hash out a deal with Senate Minority Leader Chuck Schumer

Las Vegas shooter acted alone, exact motive still undetermined: Sheriff

Stephen Paddock was behind the gunfire that killed 58 people including two Canadians

Botox, bomb shelters, and the blues: one year into Trump presidency

A look into life in Washington since Trump’s inauguration

Three-car pile-up on Northstar Drive and 58th Street

No injuries reported at Thursday afternoon incident

Suspected Toronto serial killer targeting gay community arrested

A 66-year-old man is charged with first-degree murder in disappearance of two Toronto men

Barenaked Ladies, Steven Page, to be inducted into Canadian Music Hall of Fame

Canadian band to get top honours at 2018 JUNO Awards

B.C. out of the running for Amazon’s next headquarters

Toronto is the only Canadian city left in the running despite the province backing Metro Vancouver’s bid for new Amazon headquarters

Post interest rate hike debt tips

What to do about your debt and mortgages after the interest rate hike

Most Read